Construction of new AHS: Through week of May 16

Saturday work continues

AHS project logo

UPDATED May 13: Preliminary sitework for rebuilding Arlington High School began in late February 2020, and, late that year, residents saw steel rising for one one wing. That work, Phase 1 sitework, is finished. Construction for phase 1 began in November 2020 and is nearing completion.

Construction work hours are expected to be Monday through Friday. Saturday work returned Nov. 7, 2020, and is required for the foreseeable future. 

See the new school taking shape by reading the update and viewing the photos through the week of May 16 >>

Mass. Ave. entrance and circular drive closed; district offices are accessible by the Fusco Building entrance through Schouler Court, except when access there is restricted.

To maintain the safety and health for workers and the community, the project will follow state advisories related to Covid-19, which are subject to change. The town is monitoring progress. 

Read the letter sent to abutting neighbors in 2020 >>

Learn more about the Parmenter project >>
 Geothermal wells scrapped

At the March 26, 2020, School Committee meeting, members learned that the discovery of contamination led to scrapping of geothermal wells, the planned source of electricity for the rebuilt school.

Further discussion about geothetrmal wells >> 

A public forum to discuss site work to rebuild Arlington High School was held Feb. 4, 2020, from 7 to 8:30 p.m. at Lowe Auditorium, and an estimated 70 people attended, a number with questions about rats and parking.

At the Feb. 13, 2020, School Committee meeting, Superintendent Kathleen Bodie said work would start in March that year.

Students, neighbors and visitors will start to see and hear activity on the school grounds. Join the AHS Building Committee and project partners to learn what to expect in the first three to six months of work.

This forum was of interest to parents of children in grades eight through 12 as well as neighbors in the surrounding area. Topics covered included:

  • Site work, fencing, construction and phasing plans;
  • Field closures and changes to the existing site;
  • Access changes for pedestrians/bikes/cars, parking;
  • Noise and dust control mitigation; and
  • Questions and answers
Project timeline at a glance

The project is currently in the design-development phase (summer 2019 - summer 2020) when all aspects of the design for the new school will be made final. With site work starting after February vacation, building construction will begin in October.

The first wing of the new building is expected to be open to students in late February 2022, and the school fully constructed in 2024 (followed by one year of additional site work).

To receive frequent construction updates, sign up for the new AHS construction updates here >> 

Note: Construction updates are not the same as project eBulletins, which will continue to provide general project information on a bimonthly basis.

For more information, visit www.ahsbuilding.org.


Dec. 20, 2019: $24.7M in cuts bring budget for rebuilt AHS into line

Dec. 14, 2019: About $5M cut from cost gap for new AHS design
Nov. 22, 2019: Estimate for new AHS design shows $29.5M gap
June 14, 2019: A special election: AHS rebuild, override OK'd with strong support 
Feb. 20, 2019: AHS rebuild committee sends schematic design to state agency
Feb. 6, 2019: Official vote backs cost of rebuilt AHS at $291.4M 

This news announcement was published Thursday, Jan. 16, 2020, and updated May 13, 2022.

Your Businesses

Latest comments

John Yurewicz Alewife Brook sewage campaign: Support from Ellen Mass
05 March 2022
The Thorndike Place apartment and pavement construction will re-direct natural underground aquifers ...
Bob Sprague Letters: Emailing Advocate? Copy it here. Roe v. Wade?
17 January 2022
Let the public know with a letter to the editor. For details, see https://www.yourarlington.com/easy...

Housing Authority

Your People

Lt. Dan Kelly

Retired Arlington police lieutenant dies at 58

Lt. Dan Kelly Lt. Dan Kelly, a retired member of the Arlington Police Department, died Tuesday, May 3, after fighting cancer for several years, Chief Julie Flaherty said in a report by YourArlington partner Patch. Kelly, 58, served 32 years as a decorated member of the Arlington Police Department.…
Sulinha Boucher, 2022

Younger than 5: 4th album for Arlington musician

Sulinha Boucher “We Should Be Kind." Listen to it here >> Sulinha Boucher, an Arlington musician for 30 years who is originally from Brazil, has recorded her fourth album for children, “We Should Be Kind." Perhaps you have heard her at the Robbins and Fox libraries, where she has performed for the…
Tony and Jeff Whittemore head for Montreal.

Film premieres pony tale: When 2 boys went to Montreal

Tony and Jeff Whittemore head for Montreal. / 1967 family photo UPDATED April 29: In 1967 two young boys and their beloved pony took off on a monthlong adventure that brought them fame, fun and a wealth of great stories. Tony Whittemore, 11 at the time, and his brother Jeff, 9, drove a pony cart…






FACEBOOK BOX: To see all images, click the PHOTOS link just below

 



Support YourArlington

An informed Arlington
keeps democracy alive

Donate Button

YourArlington is a 501(c)(3) nonprofit.

Your contributions are tax-deductible.

Wednesday Newsletter

Your Arts

Your Police, Fire

Development

Site Partners

Patch header

Arlington Patch

Arlington Patch has been reporting about the town since 2010. The national site with local outlets…