Night work begins in second phase of MWRA high pressure zone project

March 10, 2026

Starting on Monday, March 9, the Massachusetts Water Resources Authority (MWRA) will be completing repair work in Arlington at 1540 Mass. Ave., almost at the Lexington town line.

The work is part of the second phase of the Northern Extra High Pressure Zone Improvements Project in Arlington, Lexington, Winchester, Waltham, Bedford and Belmont.

The project will provide system redundancy in the region through the installation or replacement of approximately 14,500 linear feet of water mains and a new community meter. According to the project website, the majority of the improvements are located in Lexington and Arlington.

The night work in town is scheduled Mondays through Thursdays from 7 p.m. to 5 a.m. This work is expected to last two to three weeks.

Vehicles will continue to be able to travel in both directions along the roadway; however, new traffic patterns, signage and a police detail will be on site to assist motorists around the work site.

Additionally, during non-work hours (days and weekends) trenches will be plated, and the roadway will be open for normal traffic usage.

The MWRA will periodically distribute information as the project advances via neighborhood notifications, website updates, and electronically.


This news item, published on March 10, 2026, was written using information provided the town of Arlington and the MWRA.

Events

Free newsletter

Weather

Obituaries

Please Support Our Generous Sponsors

Judy Weinbger Leading Edge Real Estate logoIntelligent Labor and Moving logoArts Arlington logo
Go toTop

Don't Miss