Robbins Farm Playground, September 2024. / Alex Svenson photo

Robbins Farm playground, delayed as slides are made, to open this fall

September 27, 2024

Robbins Farm Playground in September. / Carol Beggy photoU

UPDATED Sept. 30: Work has begun again on the playground at Robbins Farm Park. Construction crews are working this week on installing another “roller slide,” which is a feature of the playground, according to Natasha Waden, interim director of Recreation.

Meanwhile, the two 30-foot-long concrete slides that are needed to finish the full renovation of the playground at Robbins Farm Park are being made in California. These key pieces will replace the famed hillside chutes that have anchored the playground at Robbins Farm Park for decades and need to be in place before the final work can be done to transformation of the site into the town’s first fully accessible playground.

The work at Robbins Farm started last year with an expected summer project completion. It is now scheduled to open late this fall, according to town officials.

Although the town anticipated a “significant project completion prior to July 2024,” the town’s Recreation Department recently released a report about the status of the playground’s construction, which said “there have been significant delays with the two new concrete slides,” which were “outside our team’s control.”

Second playground renovation

The playground at Robbins Farm sits almost directly across Eastern Avenue from the Brackett Elementary School, where the school’s playground is also undergoing a total renovation. Both playgrounds are closed and fenced off. Construction equipment can be seen at Robbins Farm and construction crews were working after 5 p.m. at the Brackett project this week.

That the two construction projects overlapped and left the kindergarten through fifth-grade students without a play area for recess has caused concern among parents and area residents. At least one person raised the delay on the Robbins Farm project to the School Committee during public comment at its Sept. 12 meeting.

With its extensive view of the Boston skyline, hilltop location that is ideal for wintertime sledding, a baseball diamond, and a community garden, the 11-acre Robbins Farm is one of the best-known of the town’s nearly three dozen playgrounds and parks. Robbins Farm is also a gathering site for those looking to watch the Fourth of July fireworks, dog walkers and scores of youth soccer teams.

Costs, fund-raiser

The Robbins Park renovation has an anticipated cost of $2.1 million with $997,000 in funding approved by the Community Preservation Committee and Town Meeting. The remaining funding was provided through the American Rescue Plan Act. To help the town raise enough to cover the costs of the project, the Friends of Robbins Farm Park, a community organization that promotes the beautification, restoration, and improvement of the park, launched a fund-raiser last year.

“Our group had a very successful fund-raiser to ensure that the town would be able to include some inclusive playground equipment,” said Tony Vogel, a director at the Friends of Robbins Farm Park. “We had a goal of $63,000, and we ended up raising $64,000.”

The Robbins Farm project was awarded to contractor J.J. Phelan & Son Co., whose previous work includes the first phase of the Reservoir Project and three other school playground projects – at Bishop, Peirce, and Stratton – in Arlington, and Agency Landscape and Planning, as landscape architects.

Custom-built slides

The slides are being custom-built by UPC Parks of Redding, Calif. “As soon as the slides are delivered to the site the project will then move at a much more rapid pace. Until then the contractor has very limited options as to work they can complete,” Arlington’s Park and Recreation Commission wrote in a posted update. “It is difficult to give an exact date of completion, but we are currently estimating a late fall 2024 opening. The Park and Recreation Commission realizes that this is disappointing news to the many park users.”

The commission said that the project “is valued at over $2.4 million and will be Arlington’s first playground designed with universal design principles. It is imperative that we get this project right the first time.

“Robbins Farm has had at least three other variations of metal and plastic slides over the last 30 years, but the new concrete slides are expected to be the “last slides we install at Robbins for the next 25 years. We apologize for the inconvenience and thank you for your understanding and patience as we strive to give the residents of Arlington a playground we can all be proud of,” the commission wrote in the update.

The construction in the park began in October with the demolition of the existing playground. The majority of the construction of the new playground was done last spring. Significant changes were set to be made to the play structure and the park’s iconic slides. Work at the Brackett School began on schedule, but that timeline was set before the delays at Robbins Farm.

When completed, the Brackett will have new playground equipment and a basketball court, after several years without one at the school. At Robbins Farm there is a basketball court, which is also lined for pickleball.  


Learn more about Robbins Farm Playground here >>

This news story by freelance writer Alex Svenson, with additional reporting by Carol Beggy, was published Friday, Sept. 27, 2024.