UPDATED, Dec. 3: The Arlington High School building project has reached two milestones.
Consigli Construction has committed to a final budget, while athletic complex lights and Minuteman Bikeway ramp have been added back to project.
The project marked a major success Dec. 3 when the Town of Arlington signed a guaranteed-maximum-price contract with Consigli Construction, the project’s construction manager. This is the final step in pricing the project, enabling the town to direct Consigli to proceed with building the project in its entirety.
Amy Speare reported has that the first steel went up Monday, Nov. 23, for one of the first wings of the new Arlington High School.
“Things will move quickly, and the first two wings will be framed within the next 10 weeks,” she wrote on Facebook. ACMi recorded the event (see below).
“With so much uncertainty in the world today, it is a relief to have budget stability when building a new high school,” said Town Manager Adam Chapdelaine in a Dec, 3 news release. “We’re especially pleased to be able to add back into the project a couple highly desired features.”
Items returning to the project include lighting at the new athletic fields, the Minuteman Bikeway ramp and a signal at Mill Street. The town was able to add these and other features back because of the current economy and a competitive bidding process. The contract commits Consigli Construction to a total project cost of $234,287,347.
“The project team is doing a remarkable job on the project so far,” said Jeffrey Thielman, AHS Building Committee chair, said in the release. “This milestone is an assurance to Arlington residents that the new high school will be managed to budget.”
Phase 1 construction of the first two wings of the new high school started in October and will be open to students in early 2022. The multiphase project will be completed in 2025.
“It’s exciting to see Arlington’s vision for a modern, educational environment for our students become a reality,” said schools’ Superintendent Kathleen Bodie, in the release.
The release says Consigli has a proven track record of success working on similar local school projects managed near occupied school buildings and residential neighborhoods. Consigli’s local portfolio includes work at Winchester High School, Methuen High School, Stoughton High School and Holbrook’s Pre-K-12 School as well as current assignments at Attleboro High School and Framingham’s Fuller Middle School.
Additional project partners include Skanska USA, the owner’s project manager, and HMFH Architects, the project designer.
Arlington is partnering with the Massachusetts School Building Authority to receive state funding for a significant portion of the project. Additional information, including how to subscribe to weekly construction updates, is available on the project website at www.ahsbuilding.org.
Ongoing sitework update for AHS rebuild
This news announcement was published Tuesday, Nov. 24, 2020, and updated Dec. 3.