Mass. Ave. surveying work near Menotomy Grill on May 27.
UPDATED: June 4: Facing disruption into 2016, representatives of some East Arlington businesses were among the estimated 25 local residents at the Fox Library on Tuesday, May 27, as the early steps in the Mass. Ave. Corridor project got underway.
Adam Auster reported in his Word on the Street blog, that those business owners present are choosing to celebrate instead of complain.
“Not that they have much choice,” Auster wrote, “but these businesses are determined to embrace this change, and they are bursting with creative ideas.”
The blog reported separately that signs went up Wednesday, May 28.
Ongoing Corridor photos
How about a photographic record of the Mass. Ave. Corridor project, from start to finish? You can help.
Send your photos to YourArlington, and the editor will consider them for publication.
Provide the day the photo was taken and the location. Send to sprague.bob at gmail.com.
Word on the Street, June 3: Writing on the walk
Continuing opposition, support
Longtime project critics Eric Berger and Maria Romano have made clear their stance in a statement published May 25 at YourArlington.
Meanwhile, the East Arlington Livable Streets Coalition, long a project supporter, issued a statement to its membership, not in response to the East Arlington Concerned Citizens Committee:
“After over five long years of planning and public engagement, the Mass Ave Corridor project has finally begun! For better or for worse, there was no great fanfare, nor ribbon cuttings, but as of today, the two-construction-season process is now underway.
“We are as eager as many of you to understand how exactly we and the businesses will be impacted …. Presumably, MassDOT and the contractor will present a detailed schedule for what is being done, when and where” at the June 16 public meeting at the Thompson School.
“Over the course of the next two years, we will do our best to keep you informed of what’s going on. Some EALS volunteers also plan to work with Mass Ave businesses to promote Capitol Square during construction and encourage locals to support them through all phases of construction.”
At the meeting at Fox, Auster reported businesses are discussing using banners, guerrilla art, a treasure hunt, special events and a constant flow of information aimed at turning East Arlington “into more of a destination than ever, according to Artbeat owner Jan Whitted of the Capitol Square Business Association.”
Using the motto “I can dig it” and the symbol of a butterfly, “at least some business owners are looking forward to the permanent improvements that the backhoes, cement trucks, and steamrollers will build, Auster wrote.
No weekend work, state says
Beginning the week of May 27, J.H. Lynch, MassDOT’s contractor, took initial steps to reconstruct Mass. Ave. in East Arlington.
Town Manager Adam Chapdelaine, in an update to selectmen May 19, repeated the start date as well as the June 16 meeting from a state news release and addressed the board’s concerns about communication. Later, he told YourArlington that the state plans no weekend work.
A dedicated liaison for the project, Nathaniel Cabral-Curtis, has been hired to respond to the public’s questions. He met with some East Arlington business owners the week of May 19.
For the full report up to May 27, click here >>
Sign up for project alerts
To stay abreast of its progress and upcoming schedule, sign up for email notifications by subscribing to the “East Arlington Mass. Ave. Rebuild” email list here (scroll to bottom of page).
Or you can follow progress online at arlingtonma.gov/massaverebuild.
The project will upgrade the aging infrastructure and improve safety for all users. The length of the project is estimated at two construction seasons.
Town officials understand that this will have impacts on residents, businesses and travelers in the area. In the coming months, the town will work with MassDOT to develop a detailed communication plan to keep interested parties informed of upcoming work.
Arlington’s main thoroughfare and all side streets “shall remain open to traffic at all times during the period of time required for the completion of the work,” the state Department of Transportation’s bid specifications say. “Reasonable access shall be provided by the contractor for the convenience and safe passage of pedestrians and vehicles through the project and also to the abutting properties.”
For additional information about this project, visit the state website or arlingtonma.gov/massave.
Related links to Mass. Ave. project:

Sept. 22, 2013: First report of state seeking bids
Word on the street, May 30, 2013: Mass. Ave. design clears state hurdle; U.S. decision awaited
Globe, Aug. 8, 2009: Eric Berger’s cause | E. Arlington Concerned Citizens (Part 2) | Livable Streets Coalition | Town project information
This story was published Wednesday, May 28, 2014, and updated the next day. as well as Jun4 to add a link.